A parabolic vertical curve is being designed to connect two
grades with G1 = +5% and G2 = −3%. If PVC is at station 117 +

50.00, the elevation (ft) of the PVT is most nearly:

307.21

A pavement-based dual loop detector is used to monitor
speeds of a stream of vehicles in one travel lane. The following

speeds (mph) were recorded:

45, 51, 58, 47, 50, 53, 51, 42, 61, 51

The traffic flow rate during this period is estimated to be 1,450

vphpl. The mean headway (sec) is most nearly:

2.5

The activity on arrow representation of the project is also shown
below.The critical path for the project is

ADGJ

The centerline of the local horizontal alignment of a two-lane
highway is a circular curve with radius = 915 ft. The length of curve

is 600 ft. Trees are located adjacent to the highway, as shown.

Assume standard lane width = 12 ft. The safe design speed (mph)

based on adequate sight distance is most nearly

45

A hoisting mechanism uses a cable system
as shown below. If the load W = 3 tons, the effort required (lb) at

point B is most nearly:

1715

An excavation trench is 5 ft deep, 6 ft wide, and 95 ft long.
According to OSHA standards, how many ladders are required to

provide egress from the trench?

2

An excavator has a bucket capacity of 2.8 yd3
.

Its operation cycle consists of the following phases: (a) excavation

time = 45 sec, (b) travel time (two-way) = 4 min, and (c)

dumping/transfer time = 30 sec. Assume an overall efficiency

factor for the excavator = 85%. The quantity of excavated material

= 50,000 ft3

(bank measure).

The material has the following properties:

Swell = 20%

Unit weight = 120 lb/ft3

Water content = 30%

The number of days required to complete the job, assuming 8-hr

workdays, is most nearly

11

A parabolic vertical curve joins a grade of −4% to a grade of
+6%. The PVI is at station 10 + 56.30. Elevation of the PVI is 432.65

ft. The curve passes under a bridge structure at station 12 + 00.00.

The elevation of the bottom of the bridge girders is 470.00 ft. The

minimum vertical clearance under the bridge is 14 ft 6 in. The

required length of the curve (ft) is most nearly

1665

A local municipality must make a
determination about the feasibility of repairing a bridge. The

estimated useful life of the bridge is 25 years. The MARR is 8%. The

relevant cost estimates are shown below. All costs are shown in

thousands of dollars.

The benefit-cost ratio of making repairs is most nearly:

1.11

A room is 35 ft × 25 ft in plan. Ceiling height is 14 ft. Openings
for doors and windows total 85 ft2

. The following data is given for

plastering and painting operations.

Plaster and paint crew:

1 supervisor $30/hr

1 laborer $12/hr

2 painter $18/hr

Plastering productivity = 50 ft2

/L.H.

Painting productivity = 150 ft2

/L.H.

The estimated labor cost for plastering and painting the room

(walls and ceiling) is most nearly

1280

A landfill accepts municipal solid waste from town A
population 20,000). The landfill has been in operation for 6 years

and has remaining capacity of 1,000,000 yd3

. A new subdivision

(population 5,000) is developed and populated. The waste

generation rate is 5 lb/capita-day. The average compacted density

in the landfill is 40 lb/ft3

. The reduction in the service life (years) of

the landfill due to the addition of the new subdivision is most

nearly

6

A parabolic vertical curve is to connect a tangent of +5% to a
gradient of −4%. If the PVI is at station 123 + 32.50 and the tangent

offset at the PVT is 17.65 ft, the station of the PVC is most nearly

121+36.39

Spot speed measurements are taken for vehicles passing a
given point on an urban road. Results are grouped (5-mph

intervals) as shown in the table below.

46

If the driver perception time of 2.5 sec is assumed, the
braking distance (ft) for a car on a 2% upgrade traveling at 40 mph

is most nearly

145

A car accelerates uniformly from rest to its peak speed of 70
mph. The acceleration rate is 8 mph/sec. After cruising at

maximum speed, the vehicle must brake to a complete stop,

decelerating uniformly at 10 mph/sec. If the total distance

traveled is exactly 0.5 miles, the average running speed (mph) is

most nearly

54

A horizontal curve is to be constructed for a paved rural road
in a location where the recommended superelevation is 8%. For

snow and ice conditions, the recommended value for the side

friction coefficient is 0.12. The pavement is 20 ft wide with 4-ft

shoulders. The tangents of the proposed curve are perpendicular.

The design speed for the roadway is 60 mph. The minimum length

of the curve (ft) is most nearly

1900

The coordinates (ft) of the PC and PI for a circular horizontal
curve are given below:

PC: 1232.56 N, 123.32 E

PI: 509.72 N, 172.11 W

The degree of curve = 4°

The curve deflects to the left.

The coordinates of the PT (ft) are:

130.18 S, 275.45 E

A vertical curve is being designed to connect two grades with
G1 = +2.1% and G2 = −1.5%. If the design speed is 65 mph, the

minimum length of vertical curve (ft) to satisfy AASHTO safe

stopping distance criteria is most nearly

700

A stadium hosts an event with an audience of 40,000.
Approximately 30% of the audience members are expected to use

an adjacent light rail station following the event. It is anticipated

that about 90% of the stadium empties in the first hour after the

conclusion of the event. A dedicated pedestrian walkway

connects the stadium to the light rail station. The effective width

of the walkway is 32 ft. Assume that the PHF (based on peak 15-

min flow) for the walkway is 0.88. The peak flow rate (ped/min/ft)

on the walkway during the first hour is most nearly:

6.4

An excavator having a capacity of 3 yd3 operates 8 hr in a
workday. A single cycle of operation consists of excavation, travel

(two-way), and transfer of excavated material. Cycle time for the

excavator is 8 min. Efficiency factors are:

Site 0.90

Equipment & Operator 0.72

The daily excavation production (yd3

/day) is most nearly:

115

An activity on arrow network for a project is shown below.
Numbers adjacent to arrows are activity durations (weeks).

Assume project start date is week 0. The early start date (week) for

activity G is:

11

A concrete mix has proportions 1:1.6:2.6 (cement: sand:
coarse aggregate) by weight. The following specifications are

given:

Cement

specific gravity = 3.15

94 lb/sack

Sand

specific gravity = 2.62 (SSD)

Coarse aggregate

specific gravity = 2.65 (SSD)

Added water

5.8 gal/sack cement

Air

3% (by volume)

The quantity of cement (lb/yd3

) is most nearly

670

A contractor needs to bring in 4,200 yd3 of select soil to
replace unsuitable subgrade material for a new highway. The

borrow site is located 2.6 miles away with an average round trip

travel/loading/dumping time of 30 min. The soil has a unit weight

of 125 lb/ft3 and the dump truck drivers are on 10-hr workdays.

The minimum number of 10-ton (net capacity) trucks needed to

complete the job within 8 working days is:

5

A grade beam 3 ft wide × 2 ft deep must be poured around the
perimeter of a building whose plan is shown below. The trench

excavated for the grade beam has to have 1V:1H side slopes.

Excavation is accomplished by a trackhoe, having productivity of

9 yd3

/hr. Assume an 8-hr workday.

The number of days to complete the excavation activity is most

nearly:

7

A 12-ft-high × 60-ft-long × 12-in.-thick free standing wall is to
be constructed using wall forms that are 12-ft high × 20-ft long.

Labor cost for erecting forms = $4.30/ft2

(new) and $1.30/ft2

reuse)

Labor cost for dismantling forms = $1.05/ft2

Cost of concrete (assume 10% waste) = $120/yd3

Cost of reinforcement = $25/yd3

The cost of building the wall ($) is most nearly:

9000

An embankment is to be constructed by placing fill in a 300-
ft-long section of a site. Areas of fill sections 50 ft apart are shown

in the following table. The total volume of earthwork (yd3

) between

stations 12+0.00 and 15+0.00 is most nearly:

8060

The tasks within a project, and their duration and cost data
are shown below. Both normal completion time and crashed

completion time (by allocating additional resources) are shown in

the table.

The activity on arrow representation of the project is also shown

below.

For every week of early completion, the bonus is $1,000, and for

every week that the project is late, the penalty is $800. If the

revised target completion time is 9 weeks, the net cost for

completing the project is most nearly:

26000

A horizontal compound curve connects
two tangents as shown below. The bearing of the back tangent is

N46°25′32″ E, and the bearing of the forward tangent is S17°56′21″

E. The curve radii to be used are R1 = 1,800 ft and R2 = 900 ft. The

PC is located at station 138 + 34.12 and the PI at station 158 +

12.98.

The station of the PCC is most nearly:

148+50.61

A parabolic crest curve is followed by a sag curve. The two
curves are connected by a tangent section, as shown. A bridge

structure is located at station 45 + 55.00. The elevation of the low

point on the bridge is 405.54 ft. The design speed (mph) of a truck

(assume driver’s eye elevation = 7.6 ft), based on adequate sight

distance under the bridge overpass on curve number 2, is most

nearly:

85

A circular horizontal curve connects two tangents with a
deflection angle of 42°50′. The roadway is a two-lane highway with

12-ft lanes. The centerline of the roadway has a radius of 1,245 ft.

The design speed = 50 mph. PC for the centerline circular curve is

at sta. 23 + 32.56. It is proposed to insert a pair of symmetric

spirals at the PC and the PT. The minimum length of spiral (ft) is

most nearly:

A. 120

B

160

A 6-lane freeway through rolling terrain (rural) has12-ft lanes,
interchanges every 1.25 mi and has 8-ft-wide shoulders. Traffic

studies have resulted in the following data:

AADT = 65,000 veh/day.

The traffic stream includes 8% trucks, 3% buses and 5% RVs.

K = 0.12

Peak hour factor, based on 15-min traffic counts, is 0.9.

During peak flow, directional split = 60/40.

The LOS for the peak direction of the freeway is most nearly

D

A study area is divided into three socioeconomic zones, whose trip production and trip attractions are
tabulated below:

Resistance to travel between zones is represented by the

following matrix of friction factors, which are approximately

inversely proportional to time of travel between zones.The number of trips produced by zone 3 and attracted to zone 2,

according to the first iteration of the gravity model, is most nearly:

110

A 4-lane divided highway (2 lanes in each
direction) currently has ADT of 23,000 vehicles (each way).

Approximately 12% of the traffic consists of trucks. Traffic is

expected to grow by a 4% annual rate over the next 20 years. Table

1 shows data collected from a weigh station during a typical day

for 1,078 trucks.

Using the Asphalt Institute Load Equivalence Factors (LEF) shown

in Table 2, the design 20-year 18-k ESAL (W18) is most nearly

23x10⁶

A 6-lane highway has the following characteristics:
Level terrain

Lane width = 11-ft lanes

Average spacing between accessing driveways = 600 ft

Right shoulder width = 6 ft

Clear distance to nearest obstruction in median = 4 ft

Directional hourly volume = 3,440 veh/hr

The traffic stream includes 8% trucks, 3% buses, and 2% RVs.

Peak hour factor, based on 15-min traffic counts, is 0.88.

Drivers are mostly commuters.

The LOS for the peak direction of the highway is most nearly:

C

A transition curve is to be used to implement a change in
cross-section from a normally crowned section to a fully

superelevated section. The outer lane is to be rotated from the

normally crowned section to a straight level section at the

tangent-to-spiral (T.S.) station. The roadway section is rotated

about the centerline. The following information is given:

Degree of curve (D) = 2.5°

Two 11-ft lanes

Design superelevation = 0.08 ft/ft

Grade = +1.50%

Crown = 0.015 ft/ft

P.I. station = 100 + 0.00

Deflection angle between tangents = 56°35′48″

Length of spiral = 230 ft

The station (ft) of the T.S. is most nearly

86+50

What is the recommended length of cycle for a 4-phase
signal with 3-sec lost time per phase, with the following critical

movements?

125 sec

A circular horizontal curve has PC at 12 + 43.56. Degree of
curve = 4°. Deflection angle between tangents is 56°24′45″ (right).

In order to provide adequate horizontal sightline offset at the

design speed, it is proposed to shift the forward tangent by a

parallel offset of 20 ft, while maintaining the PC, as shown in the

figure. The new degree of curve is most nearly:

3.9

A 2-lane rural freeway segment has 12-ft lanes and an 8-ft
shoulder. A cut slope of 1V:4H exists adjacent to the shoulder as

shown. The ADT is 16,000 and the design speed is 65 mph. The

minimum width (ft) measured from the edge of the shoulder,

which should be free of any obstructions, is most nearly:

38

A 2-lane Class I highway in rolling terrain has the following
characteristics:

Lane width = 12 ft, shoulder width = 6 ft

40% no passing zones

2-directional flow rate = 2,800 pc/hr

Directional split = 70/30

10% trucks and buses, 6% RVs

PHF = 0.85

For the design direction of the highway, the average travel speed

has been calculated as 42 mph and

the percent-time spent following has been calculated as 63%.

The level of service for the design direction is:

D

A horizontal circular curve is to connect a back-tangent
bearing S42°30′W to a forward tangent bearing N70°W. If the

degree of curve is 3°45′ and the tangents intersect at station 50 +

22.30, the deflection angle for station 57 + 00.00 is most nearly:

31°50'56''

A parabolic vertical curve joins a grade of −5% to a grade of
+3%. The PVC is at station 53 + 12.50 and the PVI is at station 60 +

09.00. Elevation of the PVI is 365.57 ft. The curve passes under a

bridge structure at station 55 + 05.20. The bottom elevation of the

bridge is 405.20 ft. The vertical clearance under the bridge (ft) is

most nearly:

13.4

A 2-lane highway has a circular horizontal alignment with
centerline radius of 750 ft. Lanes are 12 ft wide. An obstructing

structure exists 10 ft from the inside edge of the roadway as shown

below. The safe design speed (mph), based on adequate

horizontal sightline offset, on the curve is most nearly:

40

A horizontal curve has a radius of 1,150 ft as shown below. A
point P on the major chord is located such that AP = 215 ft. The

length of the chord offset PQ at point P (ft) is most nearly:

48

A vertical curve is being designed to connect two grades with
G1 = +2.1% and G2 = −1.5%. If the design speed is 65 mph, the

minimum length of vertical curve (ft) to satisfy AASHTO safe

stopping distance criteria is most nearly:

700

A parking lot is open during the hours of 8 A.M. to 6 P.M.
During this time, exactly 360 cars were parked on the lot; 10% for

1 hr, 15% for 2 hr, 20% for 3 hr, 30% for 4 hr, and the remaining for

the entire day. On average, 15% of the spaces are vacant and the

operational efficiency factor is 80%. The space-hr demand and

number of parking spaces in the lot are most nearly:

1,990 space-hr and 250 spaces

A 6-lane freeway through mountainous terrain has ADT of
52,500 veh/day. The traffic stream includes 8% trucks, 3% buses,

and 5% RVs. The FFS is estimated as 70 mph and the PHF = 0.9.

Directional split is 60/40 and K = 0.12.

The LOS for the peak direction of the road is most nearly:

E

A new highway with a design speed of 50 mph is to be
connected to an existing highway by a pair of reverse 2° curves.

The new highway is parallel to the existing highway, offset 80 ft to

the right.

The length of the reverse curve transition (ft), from PC to PT, is

most nearly:

960

A traffic stream has mean headways of 2.4 sec. If the jam
density is 64 veh/mi, the optimum speed is 50 mph, and the flow

is 1,500 veh/hr, then the capacity of the highway (veh/hr) is most

nearly:

1600

A 4-leg intersection in an urban location had 15 recorded
accidents (all types) during 2005. During this year, the average

daily volumes entering the intersection from the four approaches

were 1,900, 1,270, 1,620, and 930 vehicles. The intersection’s

accident rate (per hundred million entering vehicles) is most

nearly:

720

A temporary road closure (not exceeding 20
min during the daytime) is established around a 1,250-ftlong work

zone (including a buffer space) on a freeway. The distance of the

ROAD WORK AHEAD sign (ft) from the centerline of the work zone

is most nearly

5800

Ground-mounted signs are installed at the side of the road in
a commercial district where pedestrian movement or parking is

likely to occur. According to the MUTCD, the vertical distance (ft)

between the bottom of the sign and the top of the near edge of the

traveled path is most nearly:

7

In order to meet current demand, a 1-mi segment of an
urban highway must be widened by two lanes. The cost of the

improvement will be compared to a phased program of

expansion. Immediate development would cost $4,200,000 with

annual maintenance costs of $40,000. A phased program would

involve an initial investment of $2,000,000 and an estimated

expenditure of $3,200,000 in 10 years. Annual maintenance cost

under the phased program is estimated to be $28,000 for the first

10 years and $36,000 following that. Assume a perpetual period of

service for each system and MARR of 7%. The ratio of the cost for

a phased program relative to the single investment program is

most nearly:

0.85

An excavator has a bucket capacity of 2.8
yd3

. Its operation cycle consists of the following phases: (a)

excavation time = 45 sec, (b) travel time (two-way) = 4 min, and (c)

dumping/transfer time = 30 sec. Assume an overall efficiency

factor for the excavator = 85%. The quantity of material to be

excavated (bank measure) = 50,000 ft3

. The material has the

following properties:

Swell = 20%

In situ unit weight = 120 lb/ft3

Water content = 30%

Assuming 8-hr workdays, the number of days required to

complete the job is most nearly:

11

An excavator has a bucket capacity of 3.0 yd3
. Its operation

cycle consists of the following phases: (a) excavation time = 45

sec, (b) travel time (two-way) = 4 min, and (c) transfer time (to

trucks) = 45 sec. The excavator transfers the excavated material

to a fleet of trucks that carry the material offsite.

The following data is given:

Overall efficiency factor for the excavator = 90%

Truck capacity = 15 yd3

Truck cycle time (transfer + two-way travel + dumping) = 90 min

The quantity of excavated material = 2,600 yd3

(loose)

The number of trucks needed to balance the production of the

excavator, assuming 8-hr workdays, is

most nearly:

3

Dump trucks with a capacity of 16 yd3 are used to dispose of
excavated materials from a site. The distance from the dump-site

is 4 mi and the average speed of the dump trucks is 30 mph. The

bucket capacity of the power shovel is 3 yd3

; power shovel

excavation rate is 10 yd3

/min (bank measure); the transfer time to

the dump trucks (per 3-yd3 load) is 40 sec; and a dump time (per

3-yd3 load) is 30 sec. The excavated material has a swell of 10%.

The factors affecting the job site productivity of the dump truck

are: 0.80 for equipment idle time and 0.70 for operator efficiency.

If a fleet of dump trucks is used to haul the excavated material, the

number of trucks needed is most nearly:

5

A certain project includes the activities summarized in the
table below. The start date of the project is week 0. The project

duration (weeks) is most nearly:

41

Whenever a masonry wall is constructed, a
limited access zone is to be established. Which of the following is

true?

The width of the limited access zone shall be wall height
plus 4 ft.

According to OSHA, lifelines shall be secured above the point
of operation to an anchorage or structural member capable of

supporting a dead weight (lb) of at least:

5000

According to OSHA, the limiting exposure (dB) to impulse or
impact peak noise level is most nearly:

140

The Arrhenius function for concrete maturity is given below:
t20 = ∑e−

E

R

(T1

i−T1

0)Δt

where t20 = time required, when curing at 20°C, to reach an

equivalent maturity

E = activation energy = 41.5 kJ/mol for T ≥ 20°C

R = universal gas constant = 8.3144 J/(mol-K)

T0 = reference temperature = 293 K

If the average concrete temperature during curing is 28°C, the

equivalent age (days) after 3 days of curing is most nearly:

4.7

A job requires specially engineered fill to be hauled from
storage to the job site and then placed and compacted. Given the

following information the installed cost:

Compacted volume required at job site 15,000 yd3

Distance from storage to job site

32 mi

Average truck speed

32 mph

Truck capacity (net)

50,000 lb

Truck load time

25 min

Truck unload time

10 min

Truck operating cost

$80 per hr

Cost of fill at storage facility

$3 per ton

Compacted unit weight of fill

140 lb/ft3

Cost to place & compact fill

$0.50 per yd3

the ($/yd3

) of the fill is most nearly:

22

The safety log for a steel fabrication yard is shown below:
Total number of full-time employees

400

Average number of hours worked during the year 1,970

Total number of deaths

0

Total number of cases with days away from work 13 cases

Total number of days away from work

120 days

Total other recordable cases

18 cases

What is most nearly the annual total recordable case rate, as

defined by OSHA?

8

A contractor has the following options for a project lasting 18
months:

Option A:

Monthly rental of excavation equipment at

$15,000 per month + operating costs

$2,000/month

Option B:

Purchase equipment for $200,000

Maintenance costs = $8,000/month

Resale value of equipment after 18 months =

$120,000

Nominal interest rate = 10% p.a.

The benefit:cost ratio of option B (purchasing) is most nearly:

1.55

An excavation plan is outlined in the following figure. Each
grid square is 50 ft × 50 ft. The numbers are depth of cut (ft) at

indicated locations. The total volume of cut (yd3

) is most nearly:

4500

An existing landfill, in the shape of a truncated pyramid, is
rectangular at the base with plan dimensions 4,000 ft × 2,500 ft.

The free-standing sides slope 3H:1V. The height of the landfill is 12

ft. The top of the landfill must be covered with cover soil to a depth

of 18 in. The amount of cover soil (yd3) required is most nearly:

525000

The following table shows ordinates of a mass haul diagram
for a highway construction project. The free haul distance is 300

ft. Overhaul cost is $3.70/station-yd.

The total cost of overhaul is most nearly:

40000

The total duration of a project was estimated as follows:
522 working days at 6 days per week and 10 hr a day of work.

30 days (10 hr per day) for contingencies such as bad weather,

which would be worked on weekends and holidays.

The labor agreement defines the regular work day as an 8-hr-long

week-day. Labor cost for premium time is 50% for hours during the

week, and 80% for weekend work. What is most nearly the overall

labor premium rate for the project?

1.25

An activity on an arrow network for a project is shown below.
Numbers adjacent to arrows are activity durations (weeks). The

total float (weeks) for activity G is:

1

As part of the PERT analysis of a project, durations are
estimated for activities A through G and summarized in the table

below. The critical path for the project is ACEF.

The probability (%) that the project will be completed in less than

25 weeks is most nearly:

22

A new earth haul project requires moving 323,000 ft3
(bank

measure) of excavated material to a location 12 mi away. A

bidding contractor had completed a similar project (size and

scope) 2½ years ago. The proposed price for the job on record was

$525.00 per dump-truck load. Annual construction inflation factor

is 3.2%. The contractor uses a fleet of dump trucks with 26-yd3capacity (heaped). The excavated material has a swell factor of

25%. The contractor’s bid ($) should be most nearly:

326000

A crate weighing 900 lb is being lifted by four cables attached
to the corners as shown below. The attachment point for the

cables (O) is 8 ft directly above the center of gravity of the load.

Tension in each cable (lb) is most nearly:

270

It is proposed to drive a concrete pile using a pile hammer
with energy of 50,000 ft-lb. The minimum factor of safety against

bearing capacity failure is equal to 6.0. The superstructure load

transmitted to the pile is expected to be 40 tons.

The ENR pile driving equation gives the static (ultimate) bearing

capacity of a pile based on a pile driving test as:

𝐐𝐮𝐥𝐭 =

𝐖𝐇

where 𝐐𝐮𝐥𝐭 = ultimate capacity (lb)

𝐬 + 𝟏. 𝟎

𝐖 = weight of the ram (lb)

𝐇 = height the ram falls (in.)

𝐒 = pile set in in. per blow

50 blows per ft

A contract has 90 days until completion. Early completion
will be paid $18,000 bonus per day that the duration is shortened.

Activities on the critical path are targeted for “crashing.” Critical

activities can be accelerated by allocating additional crew units.

Additional cost and schedule reduction are shown in the table

below. If crews must be added as a complete unit, the net bonus

is maximized by the addition of how many crews?

1 additional crew unit

A concrete mix has the following components:
Cement

160 lb

Wet sand (moisture content = 5%)

290 lb

Wet coarse aggregate (moisture content = 3%)

420 lb

Added water

56 lb

Air

3% (by vol.)

The following specifications are given:

Cement

specific gravity = 3.15

SSD sand (m.c. = 0.7%)

specific gravity = 2.70

SSD coarse aggregate (m.c. = 0.5%)

specific gravity = 2.60

The unit weight of the concrete (lb/ft3

) is most nearly:

144

. A construction project is broken down into seven stages (AG). The sequencing of these stages is represented by a Gantt
chart, as shown. The time axis is marked in units of (5-day) weeks.

The Gantt chart shows current completion levels (shaded in gray)

superimposed on the initially planned timeline. The current status

of the project at 4 weeks 2 days is shown. Which of the following

statements is true?

Stages A and D are behind schedule.

All costs for a construction project are classified as either
direct costs (material, labor, etc.) or indirect costs (leasing and

rental costs, utilities, etc.). The estimated variation of these cost

categories vs. project duration (weeks) is shown. The optimum

project duration (weeks) is most nearly:

16

Quiz
non-communicable diseases.
egito
Aristóteles
kemi provjag vill bli godkänd
TORACE muscoli
peças de roupa em francês
biología
portugal no primeiro pos guerra
acqua
tema 14
Latin and Greek Set 8
Latin and Greek Set 9
Tema 13
vocab
Latino
evolucion de la revolucion francesa
interrogazionlatini,dallanprima alla seconda declinazione più i verbi inticativo presente attivo e passivo
Education Revision (CLASS, GENDER AND ETHNICITY)
spanska v47
5S
Psychologywhat is gender
Research Methods
Education Revision (THEORIES)
odissea
neuro systemquestions about brain, brain cells, cerebral cortex, cerebellum
Schreiben und Lesen
Termini tecnici del cinema
histologia
Tema 12
Onderdelen.Nederlands - Latijns
main connectives
tema 11
istologia
T.5 Patologia inducida por microorganismos.
sobre los articulos determinados en italianohaz un ejercico de rellenar huecos con frases en las que yo tenga que elegir que articulo determinado tengo que utilizar
Endokrina organen
text workshop D-going your own way
Bio systeme respitatoire
dalylah
げんざいりょうのほかん
KennahFILA les expressions 28-50
progra
Economia politica
German
what am i even learning atp?
T.3. Citogenética y análisis cromosómico.
Human Impact on Ecosystems
geografiateste
macbeth act2
Chapter 24 Digestive
Chapter 13 psy
clara
biology.
słowa po polsku?
FALTAS DISCIPLINARIAS
Neurochirurgia
nursing
indonesian verbs
Computer Science1.3.2
Romarriket
verbos ingles - copia
familia romana vocab
1930-1980
Antika grekland & Romarriket
Filtración glomerular
HP3 Livre
STS 2
Math true or false or fill in the blanks
Math 2nd test
SHIELA MAE QUIZ
physiqueeffet Doppler
verbos ingles
citologia
Sistemas alternativos y aumentativos de la comunicacion
conjugaciones ruso
LO6
toolbox 2
VB ANGAIS nov 14
ingles
La Euroa feudal
plugga ekologi
STATISTICA
economia
religionreligion
DanielG.E
spansk vocab
tema 10
CHAP 34 BLED
I frutta
illiade
chap 21 BLED
hemijq
sistema digestivom
cavidad bucal , boca , lengua , mejilla, labios paladar , arteria y irrigaciónl
cavidad bucal labios mejilla paladar y lengua arterias y irrigacióng
cavidad bucal con arteriasz
sistema tegumentarios
2 Parcial
contribuciones indirectas y seguridad social - copia
contribuciones indirectas y seguridad socialescribe la respuesta correcta
ima fail rq
francais
platon
le scale
bio 30 dec exam
ASDM Final
Talumpati, posisyong papel, replektibong sanaysay
vocabulaire la ville
phrased
vecka 46
Lesson 2: Political and leadership Structure
Terminologie (Radicaux) (A)
EMC frise et date introduction
mobility (emily)
histora
Espagnol interro voc.ch2quiz sur voc.chp2 espagnol
Economie semestre 1 L1
historia
L'OvinicolturaL'Ovinicoltura, allevamento degli ovini
lekrion 2
unit 3
Inglês
casse cou 5 module 3
casse cou 5 module 2
manzoni
Déchets - copie
genetics bio 2
Pragmatica e comunicazione
geografia
Physics Test 1
L'Ovinicoltura
past simple
material clothes
cuidados auxiliares de enfermería
técnicas básicas de enfermería
INF & vertaling
pattern
saúde
Voc cours d'espagol secondeBecause my teacher scares the hell out of me
De voetbeenderen.Benamingen.
casse cou 5 module 1
Lesson 1: Kinship, Marriage, and the Household
le prarticipe passe des verbes irreguliersfrans
Darija 3
allemand tâche finale chapitre 1 vocabulaire
xgbxfg
Gui
istologia animale
allemand tâche finale chapitre 1
La Consitución Española de 1978
vocabulario temporal
HCA_resumo_do_teste_(catedrais)
Histoire contemporaine
vocabulario de lugares
vocabulari tema 1
Begrepp
FRASES FETES
vocabulario general 2
vocabulario general 1
PanFil
stylistique de la poesie CM
Déchets
glosor verb
Spagnolo
cellula
Sprecheafufgaben swei. swei - copy
Sprecheafufgaben swei. swei
phlebotomy practice test
les gaz
biology
Vocabulario1. Inglés 2. Francés 3. Alemán 4. Portugués 5. Italiano 6. Catalán
Test 3 - In Class Review
Texte argumentative
scienze naturali le molecole i legami
Physical Science Final Exam
Capacitors
Preguntas y respuestas
Anglais
lagar blir till
biology 🧫🧬.
Unidad 2 Inglés
Skudde
Vocabolario ucraino
inglés
grundlagar
FRJ
Biology - 1.4.2 - many proteins are enzymes
Arabe A1 S1Exercices pour mémoriser le vocabulaire
Riksdag och regering
Grade 9 cath studies test 1
musica
för poems
friendship collocation
adjectives ed ing
begrepp
feeling and emotion
statistics
Historia
cells'
economía
hinduism grepp
Il sistema scheletricocompito in classe
sanne
Expressiones y frases en japones
elasticity
storia politica francia
biology 🧬
NGO 6.3 Samenleven
Biology - 1.4.1 - general properties of proteins
Biochemical tests
TCMTécnicas de caracterização de materiais
INFORMATICA
celtiquela periode celtiques
ses c2
philo voca
spanska muntlig
style
matchfit
Modyul 1-3
RPH FINALS
TFN FINALS
ak
segunda guerra mundial
barcelona
investigacion comercial
Hay
Graphs & Charts
Teaching Literacy Final Exam
indiapractice
Parcial 2
rod wave rap songs/ songs
rap songs
science
addition math
math multipilcation
math/algebra
perifrasis verbales
theme words hoofdstuk 2 havo 2 engels
sym chemie
stat kommun och region
habilitation
anglais
2a guerra mundial
Phrasal verbs - copia
histoire geo 2 😤
2546 Midterm 2
Reinos moneras, protoctsta y fungi
språkhistoria
ARTO SUPERIORE articolazioni
Tabla periódica
sistema solare
HidrosferaEl agua y los seres vivos, disolicion del agua, 4 propiedades principales del agua...
teknik prov årtionden
Bio chemistry notes
Chinois
svalovka
Teknik prov begrepp
TD 1 à 5 - personnes
frans
candela
acndela
Grammatik
DANA
Mots et exprssions du texte
Etapa 3